July 6, 2007, Underwood Plaza Update
The Third Floor Level structural steel beams arrived on site.
Bar joist installation at the Second Floor Level was completed, and installation of edge angles and bent plates continued.
Reinforcing steel cages for the piers at Powerhouse Row continued to be tied up.
Installation and compaction of rock fill at the central staircase was completed and reinforcing steel was installed, and stair riser forms were installed.
Electric co. ran underground conduits for power and cable into the building.
Installation of metal form decking began at the Second Floor Level.
Several of the drilled piers along the east side of Powerhouse Row were drilled, and concrete was placed.
A portion of the bar joists and floor decking for the Third Floor Level arrived.

























Bar joist installation at the Second Floor Level was completed, and installation of edge angles and bent plates continued.
Reinforcing steel cages for the piers at Powerhouse Row continued to be tied up.
Installation and compaction of rock fill at the central staircase was completed and reinforcing steel was installed, and stair riser forms were installed.
Electric co. ran underground conduits for power and cable into the building.
Installation of metal form decking began at the Second Floor Level.
Several of the drilled piers along the east side of Powerhouse Row were drilled, and concrete was placed.
A portion of the bar joists and floor decking for the Third Floor Level arrived.