January 5, 2008, Underwood Plaza Update
With falling temperatures, temporary cover and heating was put in place to allow masonry installation at the west elevation at the 2nd Floor Level to continue.
Exterior sheathing board continued to be installed at the east elevation. Felt began being installed at the east elevation.
The long west porch at the 9th Floor Level was poured.
The north entry landing at Dickson Street at the center of the building was poured.
PVC drain lines were being run over the 2nd Floor Level.
Shower pans and bathtubs continued being set at the upper floor levels.


















Exterior sheathing board continued to be installed at the east elevation. Felt began being installed at the east elevation.
The long west porch at the 9th Floor Level was poured.
The north entry landing at Dickson Street at the center of the building was poured.
PVC drain lines were being run over the 2nd Floor Level.
Shower pans and bathtubs continued being set at the upper floor levels.